E. Jelinek Ave. and Von Kanel St. Reconstruction

PROJECT OVERVIEW

The project limits are as follows:

  • E. Jelinek Avenue
    • Between Camp Phillips Road (CTH X) and Mesker Street
  • Von Kanel Street
    • Between Barbican Avenue and Schofield Avenue

This Capital Improvement Project includes the following improvements:

  • Replacement of underground drinking water and sanitary sewer utilities between Camp Phillips Road and Kirk Street.
  • Extension of underground drinking water utilities between Kirk Street and Tower Ridge Place.
  • Extension of the underground sanitary sewer utility approximately 300 feet west of Tower Ridge Place.
  • Replacement of the sanitary manhole at the intersection of E. Jelinek Avenue and Von Kanel Street.
  • Construction of new storm sewer on E. Jelinek Avenue and Von Kanel Street and replacement of street cross culverts along Von Kanel Street.
  • Construction of a multi-use path along the south side of E. Jelinek Avenue between Camp Phillips Road and Von Kanel Street and a multi-use path and sidewalk extension along the west side of Von Kanel Street between Barbican Avenue and Schofield Avenue.
  • Construction of concrete shoulder within the project limits.
  • Construction of concrete curb and gutter at intersection radii and commercial driveways.
  • Replacement of the asphalt pavement and pavement marking.

Special Assessment Meeting 4/30/2024 @ 6:00pm

Please select and follow the hyperlinks below for more information. 

PROJECT CONTACTS

STAFF ENGINEER DIRECTOR OF PUBLIC WORKS GENERAL CONTRACTOR
ISAAC DOLAN, PE
(715) 241-2634
IDOLAN@WESTONWI.GOV
MICHAEL WODALSKI, PE
(715) 241-2636
MWODALSKI@WESTONWI.GOV
MELVIN COMPANIES
1022 E. SPRUCE STREET
ABBOTSFORD, WI 54405