APRIL 2024:
Melvin Companies is the Contractor awarded the construction contract.
JUNE 2024:
Contractor plans to begin installing traffic control and erosion control devices along the project corridor.
The construction zone remains open only to local traffic going to and from their homes or businesses along E. Jelinek Avenue and Von Kanel Street. Through traffic is advised to follow speed limits and take either Barbican Avenue or Schofield Avenue to travel between Mesker Street and Camp Phillips Road (CTH X). This is for the safety of all our residents and the Contractor's crews helping our community complete this important project.
WEEK OF:
JUNE 17, 2024
The Contractor has begun work and will begin replacing the water main through the Stillwater Landing Mobile Home Community between E. Jelinek Avenue, near Kirk Street, and Schofield Avenue.
The available space is limited with the large equipment required to complete the project. The Contractor's crew will do their best to accommodate vehicles trying to get in and out of the mobile home community so please be mindful when travelling in the vicinity of the Stillwater Landing entrance. Daily water shutoffs will be required along the project limits as the crews install the new water main and transfer service from the old to the new water main.
Thank you for your patience and cooperation.
JUNE 24, 2024
The Contractor plans to continue to work on the water main replacement through the Stillwater Landing Mobile Home Community. Daily water shutoffs will be required along the project limits as the crews install the new water main and transfer service from the old to the new water main.
Thank you for your patience and cooperation.
JULY 1, 2024
The Contractor plans to complete half of the water main replacement within the Stillwater Landing Mobile Home Community and temporarily relocate to E. Jelinek Avenue to begin the sanitary sewer extension on Tower Ridge Place, between E. Jelinek Avenue and Ridge Point Circle. The Contractor does not plan to work on July 4th or July 5th.
Residents should be notified by the Contractor if they will need to temporarily park outside the project limits so that the work can be completed. These are temporary parking accommodations and should not extend more than a couple days. Residents should also be prepared to take a different route to/from their homes as work continues along E. Jelinek Avenue and the intersecting side streets.
JULY 8, 2024
The Contractor plans to finish work on the last half of the water main replacement within the Stillwater Landing Mobile Home Community and move to the sanitary sewer replacement along E. Jelinek Avenue between Camp Phillips Road and Kirk Street.
Residents should be notified by the Contractor if they will need to temporarily park outside the project limits so that the work can be completed. These are temporary parking accommodations and should not extend more than a couple days. Residents should also be prepared to take a different route to/from their homes as work continues along E. Jelinek Avenue and the intersecting side streets.
JULY 15, 2024
An update will be provided the week of July 8th.