Project to begin the week of June 17
- Construction Update for 7/18/2024
- Utility work on Alderson St from Weston Ave to Summit Ave should be finished. The crews will be working on rebuilding the roadway from Weston Ave to Summit Ave on Alderson St. This will go into the week of July 22. Concrete work for the Weston Ave and Alderson St intersection as well as Alderson St will likely begin the week of July 29.
- Construction Update for 7/11/2024
- Watermain and Sanitary Sewer have been installed. Storm sewer is currently ongoing and road building along Alderson St should start mid to late next week.
- Construction Update for 7/5/2024
- Watermain and Sanitary Sewer are being installed on Alderson St from Weston Ave to Summit Ave. Water and sewer work will continue into next week.
- Construction Update for 6/21/2024
- Weston Ave and Alderson St Intersection has been pulverized, and tree clearing at the intersection has been completed.
- Week of 6/24 will include sanitary sewer and watermain work with temporary water services being installed on Alderson St.
- Phase 1: Weston Ave and Alderson St Intersection and Alderson St
- Estimated Schedule: 6/17/24 thru 8/27/24
- Consists of the reconstruction of the Weston Ave and Alderson St intersection along with Alderson St from Weston Ave to Summit Ave. Included with this work is replacement of watermain and sanitary sewer.
- Phase 2: Summit Ave
- Estimated Schedule: 8/28/24 thru 11/18/24):
- Consists of the repaving of Summit Ave, installation of new watermain and some storm sewer addition.
- Phase 3: Weston Ave (Alderson St to Birch St)
- Estimated Schedule: 9/3/24 thru 11/18/24):
- Consists of the repaving of Weston Ave, installation of new watermain and construction of a multi-use path on the south side of the road.

Public Information Meeting Materials (3/29/2023)
Public Information Meeting Handout
Public Information Meeting Presentation