Thank you for your patience and cooperation during construction of our Village infrastructure improvement project.
WEEK OF:
JUNE 23
Mobilize equipment to Rogan Lane and begin grading infiltration basin at Kellyland Park.
MAY 2025:
Contracts were prepared and the prime contractor indicated that they plan on mobilizing equipment and materials to the project site beginning in June 2025.
APRIL 2025:
Melvin Companies is the lowest bidder and the prime contractor awarded the construction contract.