IN PROCESS & UPCOMING STREET MAINTENANCE PROJECTS - (7/30/24)
Jelinek Avenue Rehabilitation (Machmueller St - Alderson St) – Restoration and final concrete work was completed this week along with the adjustment of manholes and water valves to final heights. Those structures were then patch-paved in. Final pavement is expected for Wednesday, July 31st, weather permitting.
E. Jelinek Avenue and Von Kanel Street Reconstruction – Sanitary sewer between CR-X and Kirk St was completed this past week. Work on water main along the same stretch will continue next week. The contractor did begin working on a cross culvert on Von Kanel near CoVantage this past week as well.
Weston Avenue, Alderson Street, and Summit Avenue – The Alderson St roadway has been built up to gravel this past week. Concrete curb work is expected to start middle of this upcoming week for the roundabout and Alderson St.
Business Park Repaving – Curb and inlet repairs are anticipated to be completed this week. Milling of the existing asphalt then on Commerce Dr (RickyVal to Zinser), Zinser St (Schofield Ave to Enterprise Way), and Enterprise Way (Schofield Ave to Technology Dr) is scheduled for the middle of next week. After milling the roadways will still be passable as a gravel road, the road will then be regraded, the lower layer of asphalt placed, utility structures adjusted up to final elevations and the final layer of asphalt paved. All that should take about 2 weeks in total to complete.
CR-X Closure (Northwestern Ave to CR-N) – Marathon County will be closing CR-X between Northwestern Ave and CR-N starting Monday, July 29 through Thursday, August 1 for a culvert replacement. For more information about the County projects please see their website at: https://www.marathoncounty.gov/Home/Components/News/News/178/160