Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 8/4: Alderson St south of Schofield Ave will be continue to be closed during the week with being opened by the weekend of 8/8. Utility work along the corridor will continue along with grading the eastbound lanes.
- Week of 8/11: Storm sewer and road building will continue along the eastbound lanes.
Weston Ave (CR-X to Ryan St):
- Week of 8/4: Ryan St will be closed north of Weston Ave the week of 8/4 to get the sanitary sewer, watermain and storm sewer installed across Ryan St. Sanitary sewer work east of Heeren St towards Ryan St will continue. The base between Von Kanel and Heeren will be regraded and prepped for paving which is tentatively scheduled for later in the week.
- Week of 8/11: Sanitary sewer work will continue in both directions and once the western portion is completed, the pipe crew will then go back and start watermain work.
Fuller St:
- Week of 8/4: Pipe crew will be continuing to work from Schofield Ave heading towards the Mountain Bay Trail and the grading crew will continue working between Rogan Ln and Ross Ave.
- Week of 8/11: If grading crew completes the north portion, they will start on the southern portion of Ross Ave. Pipe crew will continue working north towards Rogan Ln.
Shorey Ave Repaving (County Road X to Anastasia Dr): This project is still on hold until work on Weston Ave can be completed through the Heeren intersection.
Weekly updates on roadway projects are released every Friday on Facebook.