Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 8/18: Storm sewer work will continue next week along with some road grading, gas line relocation and signal light work.
- Week of 8/25: Curb and Gutter is planned to be installed this week along with finishing any remaining utility work.
Weston Ave (CR-X to Ryan St):
- Week of 8/18: Crews will continue working on sanitary sewer and culvert work between Heeren and Ryan.
- Week of 8/25: Finish up sanitary and then work on watermain and laterals. Grading crew to follow areas utility crews have completed.
Fuller St:
- Week of 8/18: Concrete work will begin on Monday with curb and gutter north of Rogan to Ross Ave. Concrete will need at least 7 days of cure time after being placed so residents should park on only the west side of Fuller St to ensure one lane traffic stays open on the east side of the road. Storm sewer and watermain work will be continuing south of Rogan Ln along with grading/building of the road from Schofield Ave to the Weston Manor Mobile Home Park.
- Week of 8/25: Sidewalk work north of Rogan Ln to continue and new watermain install likely to be continuing south of Moyer Ave.
Business Park Paving (Commerce Dr and Ryan St):
- Week of 8/18: Inlets and curb and gutter work along Commerce Dr to continue with the pulverization of the existing asphalt on Commerce Dr.
Shorey Ave Repaving (County Road X to Anastasia Dr): This project is still on hold until work on Weston Ave can be completed through the Heeren intersection.
Weekly updates on roadway projects are released every Friday on Facebook.