- Monday, June 23rd - Precision Sealcoating began work crack sealing along various streets throughout the Village. This work is weather dependent but should be completed by July 11th.
- Tuesday, June 24th - Fahrner Asphalt Sealers began work asphalt sealing streets with the first section being Schofield Avenue between Ryan Street and County Highway J. This work is also weather dependent but should only take the contractor 1-2 weeks to complete.
- Wednesday, June 25th - Melvin Companies began work on the Fuller Street Reconstruction project. The contractor is starting on new storm sewer north of Rogan Lane on Fuller Street.
The Village of Weston maintains a Public Works Projects webpage, with links to specific projects and our annual Street Maintenance Projects, where project-related information is shared. Please visit the webpage to see all the different projects planned for 2025 in the Village. If there is information you’re looking for that you can’t find, please contact one of our Public Works & Utilities staff.