Weston Wisconsin is Building to Serve

Building Project News

Jan 14

January 11, 2021

Posted on January 14, 2021 at 1:29 PM by Nate Crowe

Demolition on the future site of the municipal center has begun at 4707 Camp Phillips Rd, the former site of G & B Produce.  Gene Frederickson Trucking out of Kaukauna was awarded the project with a low bid of $75,765.  The demolition portion of the project was estimated at $130,000.  They are expected to take 60 days to complete the work which would put the demolition project complete around the first week of March.
Dec 28

December 22, 2020

Posted on December 28, 2020 at 2:12 PM by Keith Donner


At the Village Board of Trustees Meeting (Video) on December 22, the Trustees adopted a resolution  to proceed with completing the design for the project, advertise for and accept bids.  The project plans will now be finalized by the architect and an alternative bid with a smaller footprint of office space will be included. The project bids will also include optional line items that the Board of Trustees can decide to include or exclude depending on need and cost.  The decision to complete design and bid the project does not commit the Village to awarding bids and continuing with the project.  However, bidding the project is the only way to be more certain of the project costs rather than continuing to speculate with historical numbers.  Further delay in taking this step also leads to increasing costs over time.

 Also during this Board Meeting, the Trustees approved a contract to proceed with demolition of the existing building at the future site of the municipal center, the northeast corner of Camp Phillips Road and Ross Avenue.  Demolition could start as soon as the first week of January.