Schofield Ave (Normandy St to Birch St):
- Week of 10/27: Topsoil Restoration and adjusting manholes and water valves in eastbound lanes is expected to be completed by Tuesday 10/28 and paving of the final layer of asphalt is scheduled to start Wednesday 10/29.
- Week of 11/3: Pavement markings to be completed.
Weston Ave (CR-X to Ryan St):
- Week of 10/27: Finish building the road to gravel base, restoration of ditches and asphalt paving is planned to begin on Friday.
- Week of 11/3: Asphalt paving to continue through the week.
Fuller St:
- Week of 10/27: Finish grading from Schofield Ave to Thomas with the first layer of asphalt planned to be paved on Tuesday. North of Thomas, asphalt driveways will be paved. Rogan Ln restoration to be done as well.
- Week of 11/3: Complete remaining seeding and restoration work and final layer of asphalt
Hospital Area Paving:
- Week of 10/27: Paving Ministry Parkway and Weston Ave inlet repairs.
- Week of 11/3: Grading Weston Ave from CR-X to Birch St and curb repairs on Birch St.