[ARCHIVED] Road Construction Update

PW Report

Schofield Ave (Normandy St to Birch St):

 

  • Week of 10/13: Finish remaining concrete work on eastbound lanes and paving of first layer of asphalt on eastbound lanes. 
  • Week of 10/20: Restoration of boulevards and medians along with utility adjustments within the pavement.  Final paving likely the following week.

 

Weston Ave (CR-X to Ryan St):

 

  • Week of 10/13: Water and sanitary sewer installation will continue west of Ryan St towards Lindenwood Ct.  Road building continuing to follow pipe crews.  Concrete curb and gutter to be poured from the ATC powerlines east to the highpoint of road on the north side. 
  • Week of 10/20: Work on completing remaining water and sanitary sewer main installation.  Start fine grading with paving then beginning the week of 10/27.

 

Fuller St:

 

  • Week of 10/13: North of Thomas Ave asphalt paving is planned Monday.  Then between Schofield Ave and Meridian, paving of the multi-use path on the east side of the road and then restoration behind the curb.  From Meridian north, curb to be poured.  Storm sewer installation along Rogan Ln from the park to Fuller St will continue. 
  • Week of 10/20: Restoration behind sidewalk and fine grading of road for paving then south of Thomas.  Possible paving from Schofield Ave north for first layer of asphalt.

 

Hospital Area Paving:

 

  • Week of 10/13: Cranberry Blvd is planned for paving.  Concrete curb work on Ministry Pkwy is continuing. 
  • Week of 10/20: Pulverizing and grading of Ministry.

Additional Info...
Facebook Twitter Email

Other News in Home - News & Announcements

Free Rabies Clinic

Posted on: March 3, 2026

The Wire - March Issue

Posted on: March 4, 2026

2026 Budget

Posted on: September 10, 2025

Notify Me

Posted on: February 22, 2024 | Last Modified on: May 19, 2025