Schofield Ave (Normandy St to Birch St):
- Week of 10/20: Topsoil Restoration and adjusting manholes and water valves in eastbound lanes.
- Week of 10/27: Complete any restoration work if needed, then paving surface layer of asphalt.
Weston Ave (CR-X to Ryan St):
- Week of 10/20: Water and sanitary sewer main lines are completed. Will be working on driveway culverts, roadway grading, and curb and gutter installation near Lindenwood Ct and at the Ryan St intersection. Road building from Ryan St heading west will continue.
- Week of 10/27: Asphalt paving will be the main item this week starting at Heeren St and heading east.
Fuller St:
- Week of 10/20: Schofield Ave intersection will be closed this week for concrete paving at the intersection. North of Thomas Ave completion of remaining restoration items. Then between Schofield Ave and Thomas, grading of the gravel base in preparation for asphalt and restoration behind the curb. Storm sewer installation along Rogan Ln from the park to Fuller St will continue.
- Week of 10/27: Paving from Schofield Ave to Thomas, complete remaining restoration work and then work on finishing up work on Rogan Ln and any remaining pond work.
Hospital Area Paving:
- Week of 10/20: Complete paving on Cranberry and then begin pulverizing and grading on Ministry along with any remaining curb and gutter repairs.
- Week of 10/27: Paving on Ministry.